What Is Typically Included in a New Build Quote?
A standard new build price covers the construction of the house from foundation to practical completion. The specific inclusions depend on your contract and specifications, but the following are almost always included in a builder’s price for a turnkey or fixed-price new build in the Franklin region.Foundation and Site Preparation
The foundation is one of the first costs confirmed once geotechnical conditions are known. Most quotes include the concrete slab or suspended timber floor system, foundation walls or piles, and the earthworks required to create the building platform. If your site requires significant cut and fill due to slope or poor ground conditions, this may be priced separately as a preliminary variation once the geotechnical report is complete.Structure and Framing
Wall framing (typically timber or light steel), roof trusses, and the structural shell of the house are standard inclusions. This is the skeleton of the home and represents the majority of the build’s labour cost in the first few stages. The build programme, from framing to lock-up, generally takes eight to twelve weeks for a standard Franklin section.Roofing, Cladding, and Joinery
Roofing material (most commonly Colorsteel longrun or stone-coated steel tile in this region), external wall cladding, window and door joinery, and the associated flashings are part of the weathertight envelope and are normally included in a standard quote. Joinery upgrades, such as thermally broken aluminium frames or increased glazing ratios, may carry a specification premium depending on the selected system.Plumbing and Drainage
Internal plumbing runs, wet area waterproofing, shower, bath, basin, and toilet fixtures to the specified range, and drainage from the house to the boundary are standard inclusions. Connection from the boundary to the mains water supply or the council sewer lateral is a separate cost in most cases (covered in the exclusions section below).Electrical and Lighting
The main switchboard, internal wiring, power points, light fittings to a specified allowance, and connections to the meter box are typically included. Home automation systems, solar photovoltaic installations, EV charging infrastructure, or custom lighting designs sit outside the standard specification and are usually priced as add-ons.Insulation and Interior Lining
Wall and ceiling insulation to the current New Zealand Building Code minimums and GIB plasterboard lining are standard. New H1 energy-efficiency requirements apply to all consented builds, so compliant insulation levels should be assumed in any current new-build quote. For more on how these regulations affect your build, the BRANZ (Building Research Association of New Zealand) publishes up-to-date technical guidance for homeowners.Kitchen and Bathroom Fit-Out
A base-level kitchen and bathroom specification is included in a turnkey build, covering cabinetry, benchtops, tapware, and sanitary ware to the nominated product range. Upgrades to stone benchtops, designer tapware, or custom joinery cabinetry will increase the quote and are usually documented as specification upgrades or variations with a clear cost.Building Consent Fees
Council consent fees for the building permit are often included in a builder’s quote, though this varies by builder and contract type. Confirm this in writing before signing. Current fee schedules for the Franklin area can be verified directly through New Zealand’s official building consents and compliance portal. Consent fees for a standard residential build in the region typically range from $5,000 to $15,000, depending on the size, complexity, and which council processes the application.Site Management and Preliminary Costs
Project management time, scaffolding, site toilets, waste removal during construction, and builder’s insurance are preliminary costs that a well-structured fixed-price builder absorbs into the total quote. These are real, substantive costs that often go unnoticed in a line-item review but are built into the per-square-metre rate on a properly scoped contract. At Rag Reno’s, we run every single phase of this construction process through our proprietary 151-point quality assurance check sheet to ensure nothing gets glossed over or missed, from earthworks to the final paint inspection.Table 1: Standard New Build Inclusions vs. Common Exclusions at a Glance
| Cost Component | Standard Build Inclusions (Turnkey / Fixed-Price) | Common Exclusions (Owner Responsibility) |
| Site Excavation | Earthworks for standard building platform | Retaining walls, major rock excavation, slope stabilisation |
| Foundation | Standard concrete slab or piles (normal soil) | Specially engineered foundations (poor ground conditions) |
| Envelope | Cladding, framing, roof, standard insulation (H1 compliant) | Thermally broken joinery upgrades, custom luxury cladding |
| Utilities | Internal wiring, plumbing runs, drainage to site boundary | Service connection fees, water meter, power/fibre run from street |
| Interior | Painting, GIB lining, standard carpet/tiles | Window blinds/curtains, custom high-end floor treatments |
| Fit-Out | Kitchen cabinetry, benchtops, basic bathrooms, tapware | Freestanding appliances (fridge, washing machine, oven, etc.) |
| Consent & Project Mgmt | Council building consent fees, builders insurance, site safety | Resource consent fees, land surveying, legal boundaries |
| External Works | Basic patio/steps to doors | Boundary fencing, lawns, planting, pathways, full driveway |
What Is Not Included in New Build Costs?
Understanding exclusions is as important as knowing what is in the quote. These are the most common costs that fall outside a standard new build contract.Land
The section price is always separate from the build price. In Franklin, section prices vary considerably depending on location, size, lot shape, and the extent of existing infrastructure. Some turnkey build-and-land packages advertise a combined total, but you should always understand what each component costs independently so you can compare like for like across different offerings.Landscaping and Fencing
Lawn preparation, garden beds, retaining for garden areas, decking, and boundary fencing are almost universally excluded from builder quotes. Budget for these separately once the build reaches practical completion. A basic lawn establishment and perimeter fence for a standard Franklin section typically adds $15,000 to $40,000, depending on section size, terrain, and material choices.Driveway
Unless explicitly listed as an inclusion in your contract, the driveway is generally excluded. Some builders include a concrete crossing from the site boundary to the garage entrance, but a full concrete or sealed driveway from the street to the house is typically priced separately or added as a variation after the concrete slab is completed.Utility Connection Fees
Connecting the house to mains water, wastewater, stormwater, and gas services involves council or network provider connection fees paid directly to the utility authority. These fees sit entirely outside the builder’s quote. Budget between $5,000 and $20,000 depending on your location, the distance from the nearest main, and whether reticulated gas is available in your street. Our guide on how to start a new house build in Franklin walks through when to budget for these fees in your pre-build planning timeline.Resource Consent
If your build requires a resource consent because it does not comply with district plan rules (for example, due to a non-complying setback, height limit breach, or a restricted discretionary activity overlay), this is a separate cost paid directly to the council. Resource consents can take weeks to months and add $3,000 to $15,000 or more in council fees and professional support costs.Freestanding Appliances
Rangehood and oven, dishwasher, refrigerator, and washing machine are not included in a standard build contract. Some builders offer an appliance package as an optional line item, but this must be listed explicitly in the contract to be relied upon.Window Treatments
Curtains, blinds, and shutters are excluded from nearly all new build contracts. Budget separately for these once the build is at practical completion stage, as they are typically installed after the builder’s handover inspection.Geotechnical Investigation
Before a foundation can be designed, a geotechnical report confirms the bearing capacity and classification of the ground. This investigation is typically the buyer’s or developer’s responsibility before the builder can finalise the foundation design and price. Costs range from $2,000 to $4,500 for a standard residential site investigation.Which Costs Fall into a Grey Zone?
Some costs sit between inclusion and exclusion and depend entirely on the contract type, the builder, and the specific site. These are the items most likely to cause budget surprises if you do not clarify them in writing before signing, which can lead to costly and frustrating building delays. To prevent these types of setbacks, make sure you actively identify and plan for common mistakes to avoid in new builds. Items to specifically confirm in your contract:- Concrete driveway and pathways: sometimes included as a line item in turnkey packages, sometimes excluded entirely.
- Letterbox, clothesline, and mail slot: minor individually, but often forgotten in the specification review.
- Builder’s margin on variations: not a direct exclusion, but variation margins typically add 15 to 25 per cent on top of the trade cost for any changes made after the contract is signed.
- Engineering design fees: structural engineer and geotechnical fees may or may not be built into the builder’s quote. Confirm this specifically.
- Retaining walls: if your site requires retaining walls to create the building platform or stabilise a boundary, these are most often priced separately once earthworks conditions are confirmed.
Table 2: Typical Cost Ranges for Common Exclusions in the Franklin Region (2026)
| Exclusion Item | Estimated Cost Range (NZD, 2026) | Key Budget Driver & Variables |
| Land / Section | $350,000 – $700,000+ | Location, lot slope, and soil condition. |
| Landscaping & Fencing | $15,000 – $40,000+ | Perimeter length, terrain, planting density, and timber choices. |
| Concrete Driveway & Pathways | $8,000 – $25,000 | Total length, excavation requirements, and decorative finishes. |
| Utility Connection Fees | $5,000 – $20,000 | Council connection charges, and distance of house from street mains. |
| Resource Consent | $3,000 – $15,000+ | Infringement severity, council planning team fees, and planning fees. |
| Freestanding Appliances | $4,000 – $12,000 | Brand selections and appliance package requirements. |
| Window Treatments | $3,000 – $10,000 | Total windows, material selection (shutters vs. basic blinds). |
| Geotechnical Report | $2,000 – $4,500 | Slope, ground stability, and required test bores. |
| Retaining Walls | $5,000 – $30,000+ | Height of wall, ground slope, and engineering structural needs. |